Pre-Development Schedule:
- January 2008 - Apply for funding from
Oregon Housing and Community Services.
- March 2008 - Oregon Housing & Community Services conditionally awards all funding
requested for Little Deschutes Lodge.
- December 2008 - Construction drawings begin.
- February 2009 - Apply for Site Plan Approval.
- March 2, 2009 - Apply for Building Permits.
- April 7, 2009 - Site Plan Approval
- April 9, 2009 - Pick-Up Building Permits
- April 14, 2009 - Record Partition Plat
- April 27, 2009 - Partnership Closing (Confirmed)
- April 27, 2009 - Construction Begins (Confirmed)
Proposed Construction Schedule:
- April 27, 2009 - Off-Site Infrastructure Construction Begins
(Confirmed)
- April 27, 2009 - On-Site Earth Work Begins (Confirmed)
- May 2009 - Going Vertical (Confirmed)
- July 1, 2009 - Second Floor Deck Complete (Confirmed)
- July 21, 2009 - 2nd Storey ICFs Poured (Confirmed)
- July 27, 2009 - Trusses Placed
- November 4, 2009 - Closed-in with drywall hung
- January 2010 - Construction ends
- Late January 2010 - Scheduled Move-In (3rd or 4th week)
This schedule will be updated again on December 30, 2009.
Change is a fact of life but especially with construction projects. This
schedule is our best guess at scheduled move-in! Stay tuned!
Waiting List Information:
- Leasing Manager - Julie Cavanaugh
- Telephone - 541-390-9679
- Email -
juliecavanaugh@pacificcrestgroup.org
-
Property Management:
- Property Manager - Janet Witt
- Telephone - 541-788-5881
Project Information:
- Project Manager - Rima Wilson
- Telephone - 541-390-4037
- Email - rimawilson@pacificcrestgroup.org
-
-

|